Updates From The 2011 School Bond
Project | Begin Construction | Completion |
---|---|---|
Stadium Parking Renovations | February 2012 | July 2012 |
South Houston Elementary New Addition and Renovations |
July 2012 | July 2013 |
Queens Intermediate Replacement School |
September 2012 | March 2014 |
Veterans Memorial Sports Complex Additions and Renovations |
November 2012 | September 2013 |
Rayburn High School and South Houston High School New Competition Gymnasiums |
December 2012 | September 2013 |
Tegeler High School New Pod Addition |
December 2012 | June 2013 |
Career Technical Education High School New School |
December 2012 | June 2014 |
Keller Middle School Replacement School |
February 2013 | June 2014 |
Facility Assessment A Renovations at 18 Schools |
March 2013 | August 2013 |
Facility Assessments B Renovations at 25 Schools |
March 2013 | August 2013 |
South Shaver Elementary Replacement School |
April 2013 | June 2014 |
Gardens Elementary Replacement School |
May 2013 | June 2014 |
Middle School #11 New School |
October 2013 | February 2015 |
Parkview Middle School New School |
October 2013 | February 2015 |
Queens Middle School New School |
April 2014 | August 2015 |
Six Middle School Gymnasiums New Gymnasium Additions |
September 2014 | July 2015 |